4.1Disclosure practicesVariable56.9
4.1.1Project identificationSubvariable78.8
4.1.1.1Project reference numberIndicador80.4
4.1.1.2Project ownerIndicador97.8
4.1.1.3Sector and sub-sectorIndicador13.9
4.1.1.4Project nameIndicador97
4.1.1.5Project locationIndicador97.8
4.1.1.6Project descriptionIndicador78.3
4.1.1.7PurposeIndicador80.4
4.1.2Project preparationSubvariable45.3
4.1.2.1Environmental impactIndicador30
4.1.2.2Land and settlement impactIndicador24.3
4.1.2.3Contact detailsIndicador53.5
4.1.2.4Project budget and date of approvalIndicador69.1
4.1.2.5Funding sourcesIndicador97.8
4.1.3Execution contract procurementSubvariable64.8
4.1.3.1Procuring entity and contact detailsIndicador69.6
4.1.3.2Procurement processIndicador82.6
4.1.3.3Number of firms biddingIndicador17.4
4.1.3.4Contract typeIndicador65.2
4.1.3.5Contract titleIndicador63
4.1.3.6Contract priceIndicador82.6
4.1.3.7Contract start dateIndicador69.6
4.1.3.8Contract durationIndicador80.4
4.1.3.9Contractor(s)Indicador54.8
4.1.3.10Contract scope of workIndicador63
4.1.4Supervision contract procurementSubvariable67.8
4.1.4.1Procuring entity and contact detailsIndicador65.7
4.1.4.2Procurement processIndicador78.3
4.1.4.3Number of firms/individuals biddingIndicador54.3
4.1.4.4Contract typeIndicador71.7
4.1.4.5Contract titleIndicador71.7
4.1.4.6Contract priceIndicador76.1
4.1.4.7Contract start dateIndicador67.4
4.1.4.8Contract durationIndicador71.7
4.1.4.9Contract firm/individualIndicador55.7
4.1.4.10Contract scope of workIndicador65.2
4.1.5Execution contract implementationSubvariable20
4.1.5.1Variation to contract priceIndicador19.6
4.1.5.2Reasons for price changesIndicador17.4
4.1.5.3Variation to contract durationIndicador23.9
4.1.5.4Reasons for contract duration changesIndicador21.7
4.1.5.5Variation to contract scopeIndicador19.6
4.1.5.6Reasons for scope changesIndicador19.6
4.1.6Supervision contract implementationSubvariable62.3
4.1.6.1Variation to contract priceIndicador60.9
4.1.6.2Reasons for price changesIndicador60.9
4.1.6.3Variation to contract durationIndicador63
4.1.6.4Reasons for duration changesIndicador63
4.1.6.5Variation to contract scopeIndicador63
4.1.6.6Reasons for scope changesIndicador63